North Maple Street Improvements

February 2021: Michael Baker, Inc is currently conducting right-of-way acquisition for Maple Street. Final construction documents are prepared and were submitted to SCDOT for review in April 2020. SCDOT provided minor comments in October 2020. Baker addressed those comments and has resubmitted and awaiting approval from SCDOT. The asbestos abatement of four properties that are to be demolished will get underway on February 15, 2021. The first public hearing for the project was held May 2016. The second public meeting was held August 2017. 